Appian Certified Senior Developer ACD200 Question # 11 Topic 2 Discussion

Appian Certified Senior Developer ACD200 Question # 11 Topic 2 Discussion

ACD200 Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

In Scrum, who is the right person responsible for prioritizing product backlog? (Choose the best answer.)


A.

Tester


B.

Product Owner


C.

Lead Developer


D.

Product Manager