Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 10 Topic 2 Discussion

APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 10 Topic 2 Discussion

AgilePM-Practitioner Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

AgilePM-Practitioner Question 10

(What should the Developers do to ensure their estimates align with AgilePM guidance?)


A.

Use a relative estimation approach to provide useful early estimates while allowing them to be refined as more information becomes available.


B.

Estimate all identified work in precise hours and days, giving the Delivery Teams the confidence to commit to fixed deadlines before development begins.


C.

Focus estimating on only the high-priority features, leaving lower-priority items, that are less likely to be addressed until later in the Project Increment.


D.

Remind Hira that it is not possible to provide accurate estimates given the influences of VUCA on both the project and the desired Eco-spa solution.


Get Premium AgilePM-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.