CCAR-P Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

You are evaluating a Claude-based deployment for adherence to a specific regulation.

Which two steps must be completed BEFORE mapping deployment data flows to specific regulatory clauses? (Select two.)

Each correct answer presents part of the solution.


A.

Compare the in-place controls against the regulatory requirements to identify any compliance gaps.


B.

Identify the applicability of the regulation based on data types, jurisdiction, and audience.


C.

Schedule the remediation work with the engineering team based on the prioritized gap findings.


D.

Document the identified gaps along with recommended remediations and residual risk for sign-off.


E.

Inventory the vendor-provided compliance tooling and confirm which compliance affordances are in place.