Question #: 12
Topic #: 2

A portfolio manager has deleted a portfolio that is no longer relevant to the business strategy. Which is a result of this action in Workfront?


A.

Programs and projects associated with the portfolio are deleted


B.

Programs associated with the portfolio are deleted.


C.

Projects associated with the portfolio are deleted.