LEED-AP-BD+C Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A mixed-use development is located 1/2 mi. (0.80 km) from a future commuter rail line station. Which of the following pieces of information is needed when determining whether the rail line station can contribute to Location and Transportation Credit, Access to Quality Transit?


A.

Discounted rail pass availability


B.

Rail line station construction completion date


C.

Connections to transfer routes


D.

Passenger capacity